East Surrey College continues to expand its digital and technology curriculum. To support this growth, upgraded IT facilities were required that provide improved capacity, functionality and student access.

  • Ash were appointed to transform four existing classrooms in A-Block into two large, fully equipped IT suites. The refurbishment included:

    • Installation of over 40 new floor boxes to provide power and data to workstations

    • Upgraded ventilation to support higher occupancy levels

    • Servicing and optimisation of existing air-conditioning units

    • New flooring, decoration and smart lighting to create bright, professional spaces

  • The IT suites required extensive M&E adaptations, including:

    • Running new power and data routes across the floor plan

    • Ensuring all services remained coordinated with desk layouts and accessibility requirements

    • Upgrading ventilation in line with increased heat loads from IT equipment

    • Maintaining a tight programme within the summer break

    • Working above and adjacent to spaces still used by staff during periods of the works

    The increased electrical and data demand added additional complexity to sequencing and commissioning.

  • We structured the programme around M&E first, ensuring all underlying services were completed early.

    Key actions included:

    • Detailed coordination with the college’s IT department for cable management and workstation layouts

    • Early installation of power routes and floor boxes to secure sequencing certainty

    • Servicing AC units before final decoration to avoid rework

    • Ensuring flooring and finishes were installed only after all cabling and testing were complete

  • The new IT suites provide:

    • Modern, high-capacity teaching spaces

    • Significantly improved power and data infrastructure

    • Enhanced ventilation and comfort for high-occupancy use

    • A clean, bright and professional environment aligned with modern digital teaching standards

    All works were delivered on time and ready for the new academic year.